FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering
SUBJECT:
title
ANNUAL PROFESSIONAL DESIGN SERVICES AGREEMENT, CONTRACT NO. FE18-00-03
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION:
Approve an increase of $70,000 to the Professional Design Services Agreement No. FE18-00-03, annual compensation limit with Dudek for a total amount not to exceed $670,000 per year.
body
BACKGROUND
Orange County Sanitation District (OC San) Professional Design Services Agreement (PDSA) No. FE18-00-03 has a task order limit of $300,000, with a maximum annual fiscal year contract award limit not to exceed $600,000.
In Fiscal Year 2020/2021, Dudek was awarded task orders for CenGen Cooling Water Pipe Replacement at Plant No. 2, Project FE20-04, for $300,000; and Olive Sub-Trunk Siphon Rehabilitation at Santa Ana River, Project No. FE20-08, for $259,867, for a total amount of $559,867.
The task order limit of CenGen Cooling Water Pipe Replacement at Plant No. 2, Project FE20-04, was increased from $300,000 to $370,000, to complete the remaining construction, commissioning, and close-out services, at the approval of the Board in October 2024 in accordance with OC San's Purchasing Ordinance.
RELEVANT STANDARDS
* Ensure the public's money is wisely spent
PROBLEM
The annual fiscal year contract award limit for PDSA No. FE18-00-03 was inadvertently not increased when the Board approved the increase to Project No. FE20-04 and now totals $629,867.
PROPOSED SOLUTION
Increase PDSA No. FE18-00-03 annual compensation limit from $600,000 to $670,000 to accommodate already approved contracts and contingencies.
TIMING CONCERNS
OC San has already authorized work based on the approved higher task order limit, and there are outstanding invoices for both Project Nos. FE20-04 and FE20-08 that cannot be paid because they exceed the maximum annual fiscal year contract award limit.
RAMIFICATIONS OF NOT TAKING ACTION...
Click here for full text