File #: 2023-3279    Version: 1 Name:
Type: Consent Status: Passed
File created: 10/17/2023 In control: OPERATIONS COMMITTEE
On agenda: 12/6/2023 Final action: 12/6/2023
Title: PUMP STATION PORTABLE GENERATOR CONNECTORS, PROJECT NO. FE19-01
Sponsors: Mike Dorman
Attachments: 1. Agenda Report
Related files: 2021-1657, 2021-1840, 2023-3350
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering

SUBJECT:

title
PUMP STATION PORTABLE GENERATOR CONNECTORS, PROJECT NO. FE19-01
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION: Recommend to the Board of Directors to:

Approve a contingency increase of $72,449 (6%) to the contract for Pacific International Electric Company, Inc., dba Pacific Industrial Electric, for Pump Station Portable Generator Connectors, Project No FE19-01, for an already approved total contract amount not to exceed $1,207,479; and a total contingency of $193,197 (16%).
body

BACKGROUND

The Orange County Sanitation District (OC San) is providing portable generator connectors at 13 pump stations and Power Building 5 at Plant No. 1 to ensure critical loads can be easily powered during a power outage or maintenance of major electrical equipment.

RELEVANT STANDARDS

* Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder
* Provide a safe and healthy workplace

PROBLEM

Unforeseen conditions encountered during construction have resulted in higher-than-expected contract changes. Part of the contractor's scope of work is to replace existing circuit breakers with new circuit breakers. The motor control center (MCC) manufacturer required the circuit breakers, along with their associated buckets, to be replaced to maintain the existing Underwriters Laboratory (UL) rating of the MCCs. Typically, a UL circuit breaker can be replaced with another UL circuit breaker and still maintain the UL rating. The cost of this work has substantially impacted the approved construction contract contingency; therefore, the remaining contingency is estimated to be insufficient to complete construction.



PROPOSED SOLUTION

Approve an increase of $72,449 (6%) to the contract contingency, for a total contingency of $193,197 (16%). This increase will cover additional cost...