Title: PLANT NO. 2 SPARE MAIN SEWAGE PUMP
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report
Related files: 2020-943
FROM: Robert Thompson, General Manager
Originator: Riaz Moinuddin, Director of Operations & Maintenance

SUBJECT:

title
PLANT NO. 2 SPARE MAIN SEWAGE PUMP
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION: Recommend to the Board of Directors to:

A. Approve a Sole Source Purchase Order to DXP Enterprises, Inc., dba CorTech Engineering, LLC for one spare Patterson Main Sewage Pump (MSP) for a total amount not to exceed $393,163; and

B. Approve a contingency of $39,316 (10%).
body

BACKGROUND

Orange County Sanitation District (OC San) Plant No. 2 operates seven Main Sewage Pumps (MSPs) that convey incoming wastewater from the collection system through the headworks to downstream treatment processes. MSPs 1 through 3 serve non-reclaimable flows, while MSPs 4 through 7 serve reclaimable flows. These pumps provide a combined maximum influent pumping capacity of 322 million gallons per day (MGD) and are essential to maintaining reliable wastewater conveyance and treatment operations.

RELEVANT STANDARDS

24/7/365 treatment plant reliability
Protect OC San assets
Protect public safety
Maintain a proactive asset management program

PROBLEM

OC San does not currently have a compatible spare MSP. The existing Patterson pumps cannot be overhauled by OC San and must be sent off-site for major repairs. A pump failure could therefore result in extended downtime, reduced pumping capacity, and increased risk of treatment interruptions, particularly during peak flow conditions.


PROPOSED SOLUTION

Procure one spare Patterson MSP through DXP Enterprises, Inc., dba CorTech Engineering, LLC, the manufacturer's authorized representative, to minimize equipment downtime and maintain influent pumping reliability.

TIMING CONCERNS

The spare MSP has an estimated 12-week procurement lead time. Delaying procurement increases the risk of prolonged equipment downtime and reduced pumping capacity should an existing pump fail.

RAMIFICATIONS OF NO...