Legislation Details

File #: 2026-4918    Version: 1 Name:
Type: Non-Consent Status: Final
File created: 5/12/2026 In control: OPERATIONS COMMITTEE
On agenda: 12/2/2026 Final action:
Title: ADMINISTRATIVE FACILITIES DEMOLITION, PROJECT NO. P1-141
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Construction Contract, 3. Presentation
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering

SUBJECT:

title
ADMINISTRATIVE FACILITIES DEMOLITION, PROJECT NO. P1-141
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION: Recommend to the Board of Directors to:

A. Receive and file Bid Tabulation and Recommendation for Administrative Facilities Demolition, Project No. P1-141;

B. Award a Construction Contract to Icon West, Inc. for Administrative Facilities Demolition, Project No. P1-141, for a total amount not to exceed $5,594,000; and

C. Approve a contingency of $559,400 (10%).
body

BACKGROUND

The Orange County Sanitation District’s (OC San) Administration and Human Resources Buildings at Plant No. 1 were vacated after the completion of the Headquarters Building.

RELEVANT STANDARDS

Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder
Ensure the public’s money is wisely spent
Sound engineering and accounting practices, complying with local, state, and federal laws

PROBLEM

The Administration and Human Resources Buildings are no longer needed and require demolition.

PROPOSED SOLUTION

Award a construction contract to demolish the vacant Administration and Human Resources Buildings. The cleared site will be used for additional parking, public tour activities, and contractor staging while remaining available for future treatment facilities.

TIMING CONCERNS

Delaying the construction contract award would postpone demolition and the site’s availability for additional fleet parking and future contractor staging for Project No. P1-126, Primary Sedimentation Basins No. 3-5 Replacement at Plant No. 1.

RAMIFICATIONS OF NOT TAKING ACTION

Without awarding the construction contract, the existing Administration and Human Resources Buildings will remain in place, and ongoing maintenance costs for the vacant facilities will continue to accrue....