File #: 2022-2152    Version: 1 Name:
Type: Consent Status: Passed
File created: 2/15/2022 In control: OPERATIONS COMMITTEE
On agenda: 3/16/2022 Final action: 3/16/2022
Title: REIMBURSEMENT AGREEMENT FOR ORANGE COUNTY SANITATION DISTRICT MANHOLE FRAME AND COVER ADJUSTMENTS ON EUCLID STREET IN THE CITY OF ANAHEIM
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. Draft Reimbursement Agreement
FROM: James D. Herberg, General Manager
Originator: Kathy Millea, Director of Engineering

SUBJECT:

title
REIMBURSEMENT AGREEMENT FOR ORANGE COUNTY SANITATION DISTRICT MANHOLE FRAME AND COVER ADJUSTMENTS ON EUCLID STREET IN THE CITY OF ANAHEIM
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

Approve and authorize the General Manager to execute a Reimbursement Agreement with the City of Anaheim for an amount not to exceed $180,000 for Orange County Sanitation District manhole frame and cover adjustments on Euclid Street in the City of Anaheim in a form approved by General Counsel.
body

BACKGROUND

The City of Anaheim (City) is working on a street rehabilitation project on Euclid Street from Broadway to the 91 Freeway. This project generally consists of asphalt pavement resurfacing and associated improvements within the existing right-of-way. Orange County Sanitation District (OC San) is responsible for adjusting the elevation of its infrastructure in the public right of way in order to maintain road safety and system function.

The City intends to award the paving contract on March 01, 2022 which will include pricing to adjust OC San's manholes effected by the contract.

RELEVANT STANDARDS

* Protect OC San assets
* Maintain collaborative and cooperative relationships with regulators, stakeholders, and neighboring communities

PROBLEM

OC San owns 39 manholes within the limits of the City's project. These manholes will need to be adjusted to a final grade after the City resurfaces the pavement to maintain road safety and system function.


PROPOSED SOLUTION

Enter into a reimbursement agreement with the City for the City's awarded contractor to perform the manhole adjustment work. OC San will provide the manhole frames and covers to the City, as well as inspection services to ensure the construction is in conformance with OC San standards.

TIMING CONCERNS

The Project is anticipated to start in April 2022 and be complete...

Click here for full text