File #: 2023-3348    Version: 1 Name:
Type: Consent Status: Passed
File created: 12/4/2023 In control: OPERATIONS COMMITTEE
On agenda: 12/14/2023 Final action: 12/14/2023
Title: CONTROL CENTER OFFICES AND DAY TRAINING ROOM REMODELING AT PLANT NO. 1, PROJECT FR1-0007R
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. FR1-0007R Contract Agreement
Related files: 2023-2955
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering

SUBJECT:

title
CONTROL CENTER OFFICES AND DAY TRAINING ROOM REMODELING AT PLANT NO. 1, PROJECT FR1-0007R
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

A. Receive and file Bid Tabulation and Recommendation for Control Center Offices and Day Training Room Remodeling at Plant No. 1, Project No. FR1-0007R;

B. Award a Construction Contract to A 2 Z Construct, Inc. for Control Center Offices and Day Training Room Remodeling at Plant No. 1, Project No. FR1-0007R, for a total amount not to exceed $348,000; and

C. Approve a contingency of $34,800 (10%).
body

BACKGROUND

The Control Center Building at Orange County Sanitation District (OC San) Plant No. 1 is a two-story office building housing mainly operations staff. The Day Training Room in this building is typically used by 17 Plant Operators during day shift and seven Plant Operators during night shift, including four Lead Operators. The room is also used for frequent meetings among operators.

OC San workspace standards call for four-foot-wide workstations for Plant Operators, eight-foot by eight-foot cubicles for Lead Plant Operators, and approximately 10-foot by 10-foot individual offices for Supervisors. Operator workstations are not dedicated to individual Operators, so the same workstations are used by more than one Operator over the course of a day. Individual offices are needed for supervisors to conduct sensitive and private discussions with staff.

OC San awarded a previous FR1-0007 Contract in May 2021 and the Contractor failed to perform in accordance with the contract and scope of work for the project. The contract work was not completed, which required a readvertise of the project under FR1-0007R. Only the Day Training Room demolition work was performed, resulting in the inability to use this space.



RELEVANT STANDARDS

* Comply with California Public Cont...

Click here for full text