File #: 2023-3091    Version: 1 Name:
Type: Consent Status: Passed
File created: 7/6/2023 In control: OPERATIONS COMMITTEE
On agenda: 7/26/2023 Final action: 7/26/2023
Title: MACARTHUR FORCE MAIN IMPROVEMENTS, PROJECT NO. 7-68
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. 7-68 Professional Construction Services Agreement
Related files: 2023-2896
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering

SUBJECT:

title
MACARTHUR FORCE MAIN IMPROVEMENTS, PROJECT NO. 7-68
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

A. Approve a Professional Construction Services Agreement with Michael Baker International, Inc. to provide construction support services for MacArthur Force Main Improvements, Project No. 7-68, for a total amount not to exceed $272,002; and

B. Approve a contingency of $27,200 (10%).
body

BACKGROUND

Michael Baker International, Inc. was selected as part of a competitive, qualifications-based solicitation process to design MacArthur Force Main Improvements, Project No. 7-68. At the time of the solicitation, the Orange County Sanitation District (OC San) documented its intent to award a subsequent agreement to the design consultant for the continuation of engineering services during construction.

OC San owns and operates a 12-inch asbestos cement force main that conveys flows from the MacArthur Pump Station and discharges into a manhole in Birch Street in the City of Newport Beach. This force main, built in the 1960s, is approximately 2,100 feet long, and is located in an OC San easement below the sidewalk on MacArthur Boulevard.

RELEVANT STANDARDS

* Comply with California Government Code Section 4256 to engage the best qualified firm "on the basis of demonstrated competence and qualifications" and "negotiate fair and reasonable fees"
* Ensure the public's money is wisely spent

PROBLEM

This project requires the design consultant to provide as-needed services during construction including submittal review, responding to the contractor's requests for information, reviewing construction change orders, participating in meetings, attending site visits, and preparing record drawings.

PROPOSED SOLUTION

Approve a Professional Construction Services Agreement with the design consultant, Michael Baker International, Inc....