Legislation Details

File #: 2026-5060    Version: 1 Name:
Type: Non-Consent Status: Final
File created: 8/17/2026 In control: OPERATIONS COMMITTEE
On agenda: 9/2/2026 Final action:
Title: MANHOLE FRAME AND COVER REPLACEMENT SERVICES, SPECIFICATION NO. S-2026-729BD
Sponsors: Riaz Moinuddin
Attachments: 1. Agenda Report, 2. S-2026-729BD General Services Contract, 3. Presentation - Manhole Frame and Cover Services
Related files: 2021-1848
FROM: Robert Thompson, General Manager
Originator: Riaz Moinuddin, Director of Operations & Maintenance

SUBJECT:

title
MANHOLE FRAME AND COVER REPLACEMENT SERVICES, SPECIFICATION NO. S-2026-729BD
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION: Recommend to the Board of Directors to:

A. Approve a General Services Contract to Ayala Engineering, Inc. to provide Manhole Frame and Cover Replacement Services, Specification No. S-2026-729BD, for a total amount not to exceed $1,260,350 for the period beginning November 1, 2026, through October 31, 2027, with four (4) one-year renewal options; and

B. Approve an annual contingency of $126,035 (10%).
body

BACKGROUND

The Orange County Sanitation District (OC San) owns approximately 4,483 manholes throughout Orange County. Occasionally, manholes need repair or replacement due to corrosion, traffic-related wear, settlement, aging, or street repaving. Public safety requires worn manhole frames and covers to be repaired in a timely manner. In addition, when street repaving occurs, OC San is required to reset its manhole frames and covers to match the new street elevation.

RELEVANT STANDARDS

Operate and maintain facilities to minimize impacts on surrounding communities, including odor, noise, and lighting
Protect OC San assets
Commitment to safety & reducing risk in all operations

PROBLEM

The current Manhole Frame and Cover Replacement Services contract expires on October 31, 2026. Without a replacement contract, OC San would not have an efficient contracting mechanism to address deficient frames and covers.


The existing contract supports the repair or replacement of more than 100 manhole frames and covers annually. Deficiencies are identified through reports from members of the public and city partners, as well as inspections by OC San Engineering and field staff.

PROPOSED SOLUTION

Approve a General Services Contract with Ayala Engineering, Inc. to continue timely ...