Title: PROCESS CONTROL SYSTEMS UPGRADE, PROJECT NO. J-120
Sponsors: Mike Dorman
Attachments: 1. Agenda Report
Related files: 2021-1762, 2023-2802, 2023-2975
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Acting Director of Engineering

SUBJECT:

title
PROCESS CONTROL SYSTEMS UPGRADE, PROJECT NO. J-120
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION: Recommend to the Board of Directors to:

A. Approve a Purchase Order to CDW-G Corporation for the purchase of computers and monitors, for the Process System Control Upgrade, Project No. J-120, using the Sourcewell cooperative contract number 081419-CDW for a total amount not to exceed $334,058 plus applicable sales tax; and

B. Approve a contingency of $33,406 (10%).
body

BACKGROUND

Process Control Systems Upgrade, Project No. J-120, will replace the existing Human-Machine-Interface (HMI) system and data historian with an ABB distributed control system (DCS). The HMI system is the graphical user interface for Orange County Sanitation District's (OC San) treatment plants and collections facilities control systems.

The new DCS requires computer workstations, monitors, and ancillary items which were not included in Project No. J-120 under the Master Services Agreement with ABB Inc. and were planned as owner-furnished equipment. The items selected meet ABB's recommended specifications and OC San's standards.

RELEVANT STANDARDS

* 24/7/365 treatment plant reliability
* Participate in local, state, and national cooperative purchasing programs
* Ensure the public's money is wisely spent
* Maintain a culture of improving efficiency to reduce the cost to provide the current service level or standard
* Protect OC San assets



PROBLEM

The new DCS system requires computer workstations and monitors to be functional. The existing workstations used for the existing HMI system do not meet ABB's recommended specifications. Staff will not be able to use the new system if workstations are not purchased.

PROPOSED SOLUTION

Approve a purchase order for computers and monitors utilizing a cooperative agreement.