FROM: Robert Thompson, General Manager
Originator: Riaz Moinuddin, Director of Operations & Maintenance
SUBJECT:
title
JANITORIAL SERVICES AT ORANGE COUNTY SANITATION DISTRICT HEADQUARTERS COMPLEX
end
GENERAL MANAGER'S RECOMMENDATION
recommendation
RECOMMENDATION: Recommend to the Board of Directors to:
A. Approve a Purchase Order Agreement with Team One Management for Janitorial Maintenance Services at the Orange County Sanitation District's (OC San) Headquarters Complex, utilizing the County of Orange Contract No. MA-012-22011179, from the Notice to Proceed through January 31, 2025, for a total amount not to exceed $458,400; and
B. Approve a contingency of $45,840 (10%).
body
BACKGROUND
Orange County Sanitation District (OC San) is in the final phase of constructing a new Headquarters Complex under Project No. P1-128A. With an anticipated move-in date in the first quarter of 2024, the 109,000 square feet Headquarters Complex will require daily janitorial and cleaning services, including all necessary labor, supplies, materials, and equipment. There will be a short overlap period where the existing buildings and the new Headquarters Complex will both require cleaning services.
RELEVANT STANDARDS
* Commitment to safety & reducing risk in all operations
* Provide a safe and collegial workplace
PROBLEM
The Headquarters Complex for OC San is not included in the current janitorial agreement. As employees occupy the building, a janitorial service agreement will be needed to keep the lobby, offices, meeting rooms, lunch areas, and restrooms cleaned and maintained.
PROPOSED SOLUTION
Approve a purchase order agreement with Team One Management.
TIMING CONCERNS
A janitorial agreement will need to be in place before staff occupies the building in the first quarter of 2024.
RAMIFICATIONS OF NOT TAKING ACTION
Without a janitorial agreement, there will be no janitorial or cleaning services at OC San's Headquarters Complex.
PRIOR CO...
Click here for full text