File #: 2024-4005    Version: 1 Name:
Type: Consent Status: Passed
File created: 12/5/2024 In control: OPERATIONS COMMITTEE
On agenda: 12/18/2024 Final action: 12/18/2024
Title: NEWHOPE-PLACENTIA SEWER MANHOLE REPLACEMENTS, PROJECT NO. FE21-08
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Construction Contract Agreement - FE21-08
Related files: 2024-3417
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Director of Engineering

SUBJECT:

title
NEWHOPE-PLACENTIA SEWER MANHOLE REPLACEMENTS, PROJECT NO. FE21-08
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

A. Receive and file Bid Tabulation and Recommendation for Newhope-Placentia Sewer Manhole Replacements, Project No. FE21-08;

B. Award a Construction Contract Agreement to Sancon Technologies, Inc., for Newhope-Placentia Sewer Manhole Replacements, Project No. FE21-08, for a total amount not to exceed $406,730; and

C. Approve a contingency of $81,346 (20%).
body

BACKGROUND

The Orange County Sanitation District (OC San) operates an extensive network of sewer infrastructure, and as part of its ongoing maintenance and modernization efforts, three manholes in the Newhope-Placentia Trunk Sewer (NHP) system were identified for potential replacement. Originally constructed in 1958, these manholes had sustained significant deterioration due to hydrogen sulfide corrosion, a common issue in wastewater systems. However, after a more detailed evaluation, it was determined that rather than full replacement, the manholes could be rehabilitated to meet modern standards and extend their functional lifespan.

RELEVANT STANDARDS

* Comply with California Public Contract Code Section 20103.8, award construction contract to lowest responsive, responsible bidder
* Commitment to safety & reducing risk in all operations

PROBLEM

Three NHP manholes are severely corroded. Hydrogen sulfide corrosion has eroded the concrete extensively, leaving the reinforcing rebar exposed.

PROPOSED SOLUTION

Award a construction contract agreement for Newhope-Placentia Sewer Manhole Replacements, Project No. FE21-08. This project will rehabilitate the three manholes to extend their service life ranging between 25 to 50 years depending on the rehabilitation approach.

A 20% contingency is requested due to the higher level of risk...