File #: 2019-601    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 9/19/2019 In control: OPERATIONS COMMITTEE
On agenda: 9/25/2019 Final action: 9/25/2019
Title: RETURN ACTIVATED SLUDGE PIPING REPLACEMENT AT PLANT NO. 2, PROJECT NO. P2-123
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. Professional Construction Services Agreement, 3. 09-04-19 Operations Committee Presentation
Related files: 2019-512
FROM: James D. Herberg, General Manager
Originator: Kathy Millea, Director of Engineering

SUBJECT:

title
RETURN ACTIVATED SLUDGE PIPING REPLACEMENT AT PLANT NO. 2, PROJECT NO. P2-123
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

A. Approve a Professional Construction Services Agreement with Spec Services, Inc. to provide construction support services for Return Activated Sludge Piping Replacement at Plant No. 2, Project No. P2-123, for a total amount not to exceed $252,329; and

B. Approve a contingency of $25,233 (10%).
body

BACKGROUND

Orange County Sanitation District's (Sanitation District) Plant No. 2 has two biological secondary treatment facilities, one of which is the Activated Sludge Plant, which uses pure oxygen for wastewater treatment. The Activated Sludge Plant was built in 1979 and includes a concrete deck that seals oxygen into the process basins and ninety-two light poles and fixtures installed throughout the facility to provide operators safe working conditions at night.

RELEVANT STANDARDS

* 24/7/365 treatment plant reliability
* Comply with California Government Code Section 4256 to engage the best qualified firm "on the basis of demonstrated competence and qualifications" and "negotiate fair and reasonable fees"

PROBLEM

The project requires the design consultant to provide as-needed services during construction including submittal review, answering the contractor's requests for information, reviewing construction change orders, participating in meetings, site visits, and preparing record drawings.

PROPOSED SOLUTION

Award a Professional Construction Services Agreement with the design consultant Spec Services, Inc., to provide engineering support services during construction.

TIMING CONCERNS

Engineering support services will be needed at the start of construction, which is anticipated for October 23, 2019.

RAMIFICATIONS OF NOT TAKING ACTION

The engineering support services needed to f...