File #: 2019-730    Version: 1 Name:
Type: Consent Status: Passed
File created: 11/7/2019 In control: OPERATIONS COMMITTEE
On agenda: 11/20/2019 Final action: 11/20/2019
Title: CAPITAL IMPROVEMENT PROGRAM CONTRACT PERFORMANCE REPORT
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. CIP Contract Performance Report Period Ending 09-30-19, 3. File Summary
Related files: 2019-668

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

CAPITAL IMPROVEMENT PROGRAM CONTRACT PERFORMANCE REPORT

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  

Receive and file the Capital Improvement Program Contract Performance Report for the period ending September 30, 2019.

body

 

BACKGROUND

 

The Capital Improvement Program involves awarding and managing many construction and consulting contracts.  In 2008, the Orange County Sanitation District (Sanitation District) Board of Directors began awarding contingencies along with construction and consulting contracts and amendments for consulting contracts up to the amount of the approved contingency.  This practice reduces administrative costs, expedites resolution of project issues that arise, helps avoid Contractor delay claims, and facilitates efficient management of many contracts.

 

The Capital Improvement Program Contract Performance Report summarizes construction and consulting contract performance and activities for the quarter ending September 30, 2019.  This report is updated quarterly.

 

RELEVANT STANDARDS

 

                     Ensure the public’s money is wisely spent

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OCSD website (www.ocsd.com) with the complete agenda package:

 

                     Capital Improvement Program Contract Performance Report for the period ending September 30, 2019