File #: 2019-732    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 11/7/2019 In control: OPERATIONS COMMITTEE
On agenda: 11/20/2019 Final action: 11/20/2019
Title: PLANT NO. 2 MAIN SEWAGE PUMPS MOTOR OVERHAUL
Sponsors: Rob Thompson
Attachments: 1. Agenda Report, 2. S-2019-1089BD Final Service Contract, 3. File Summary
Related files: 2019-553

FROM:                     James D. Herberg, General Manager

                     Originator:  Rob Thompson, Assistant General Manager 

 

SUBJECT:

 

title

PLANT NO. 2 MAIN SEWAGE PUMPS MOTOR OVERHAUL

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:  

A.       Award a service contract to R.A. Reed Electric Company to provide Plant No. 2 Main Sewage Pump Motor Overhaul, Specification No. S-2019-1089BD, for a total amount not to exceed $430,680; and

 

B.       Approve a contingency of $43,068 (10%).

body

 

BACKGROUND

 

The Orange County Sanitation District (Sanitation District) has seven Main Sewage Pumps (MSP) at Plant No. 2 Headworks to pump all the influent wastewater entering the plant for further treatment.  The MSP motors are 700 horsepower WEG electric motors and were installed during the construction of P2-66 Headworks Improvements at Plant No. 2, which lasted from 2005 to 2013. 

 

Project No. P2-122, Headworks Modification at Plant No. 2 for GWRS Final Expansion, which supports the GWRS by segregating Plant No. 2 Headworks into reclaimable and non-reclaimable sections, will modify three of the seven pumps to a lower hydraulic capacity for more efficient pumping.  The project will use the existing motors for the new pumps.

 

RELEVANT STANDARDS

 

                     Protect Orange County Sanitation District assets

                     Maintain a proactive asset management program

                     24/7/365 treatment plant reliability

 

PROBLEM

 

The enclosure type of the MSP motors is WPII, where cooling air is drawn from open atmosphere.  Air baffles are installed inside to prevent foreign materials from entering the motor, but over the long-term, foreign material tends to build up, requiring a thorough cleaning.  This cleaning requires disassembly of the motors.  The MSP motors have not been cleaned and tested since installation.

 

PROPOSED SOLUTION

 

Staff recommends a turnkey solution with R.A. Reed Electric Company for on-site field services to remove, clean, shop overhaul, test, re-install, and commission the motors.

 

TIMING CONCERNS

 

Construction of Project No. P2-122, Headworks Modification at Plant No. 2 for GWRS Final Expansion, is scheduled to start in summer of 2020.  This work requires that the existing three motors be removed from their bases.  Current plans call for completing the reconditioning of those three motors before the project begins work in the area.  The remaining four motors can be reconditioned one at a time by coordinating with the Operations and Maintenance Department and the P2-122 project team.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

There is an increased risk of failure due to loss of air cooling and consequences of rigging the motors during the P2-122 construction.  The availability of the MSPs directly correlates to the plant’s capacity and there is also an increased risk of being unable to fully support GWRS expansion.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

N/A

 

ADDITIONAL INFORMATION

 

The Sanitation District advertised a Request for Bids on August 23, 2019, Specification No. S-2019-1089BD.  Six firms showed interest and were present at the pre-bid meeting.  One bid was submitted.  Based on the Sanitation District’s standard evaluation process and pursuant to government codes, staff recommends approval of a service contract with R.A. Reed Electric Company for an amount not to exceed $430,680.

 

A ten percent contingency is recommended to address potential unknown conditions that may be uncovered during the overhaul of the motors.

 

CEQA

 

N/A

 

FINANCIAL CONSIDERATIONS

 

This request complies with authority levels of the Sanitation District's Purchasing Ordinance.  This recommendation would be funded under the Repairs and Maintenance line item for Operations and Maintenance Department (Budget Update Fiscal Year 2019-20, Page 49), and the available funding is sufficient for this action.

 

Date of Approval

Contract Amount

Contingency

11/20/2019

$430,680

$43,068

 

 

 

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OCSD website (www.ocsd.com) with the complete agenda package:

 

                     Service Contract