File #: 2020-912    Version: 1 Name:
Type: Consent Status: Passed
File created: 2/6/2020 In control: OPERATIONS COMMITTEE
On agenda: 2/26/2020 Final action: 2/26/2020
Title: WESTMINSTER BOULEVARD FORCE MAIN REPLACEMENT, PROJECT NO. 3-62
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. Sewer Relocation Agreement (Final), 3. File Summary

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

WESTMINSTER BOULEVARD FORCE MAIN REPLACEMENT, PROJECT NO. 3-62

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

Approve a Sewer Relocation Agreement between the Orange County Sanitation District and the Midway City Sanitary District.

body

 

BACKGROUND

 

Midway City Sanitary District (MCSD) operates and maintains sewers in the vicinity of the Orange County Sanitation District (Sanitation District) Knott trunk sewer that is located along Westminster Boulevard in the City of Westminster.  MCSD discharges flow into an existing Sanitation District manhole that will be modified by Westminster Boulevard Force Main Replacement, Project No. 3-62.

 

RELEVANT STANDARDS

 

                     Maintain collaborative and cooperative relationships with regulators, stakeholders, and neighboring communities

 

PROBLEM

 

Westminster Boulevard Force Main Replacement, Project No. 3-62, is replacing the sewers along Westminster Boulevard that have reached the end of their useful lives.  Construction of the sewers requires an extension of the MCSD sewers.

 

PROPOSED SOLUTION

 

Approve a Sewer Relocation Agreement between the Sanitation District and the MCSD to extend the existing MCSD force mains.  This work is included within Westminster Boulevard Force Main Replacement, Project No. 3-62.

 

 

 

 

TIMING CONCERNS

 

The Sewer Relocation Agreement must be executed prior to construction of the modified MCSD facilities.  This project is scheduled to commence in February 2020 and complete in October of 2022.

 

RAMIFICATIONS OF NOT TAKING ACTION

 

Westminster Boulevard Force Main Replacement, Project No. 3-62, could not be completed because it would not provide a connection for the MCSD force mains.

 

PRIOR COMMITTEE/BOARD ACTIONS

 

December 2019 - Awarded a Construction Contract to Teichert Energy & Utilities Group, Inc. for Westminster Boulevard Force Main Replacement, Project No. 3-62, for a total amount not to exceed $27,743,000, and approved a contingency of $2,774,300.

 

ADDITIONAL INFORMATION

 

The Sanitation District and MCSD staff coordinated the design of this relocation as part of Westminster Boulevard Force Main Replacement, Project No. 3-62.

 

CEQA

 

The project is exempt from CEQA under the Class 1, 2, 3, and 4 categorical exemptions set forth in California Code of Regulations Sections 15301, 15302, 15303, and 15304, because the project involves repair, replacement, minor alteration including land, construction or reconstruction of existing utility systems involving negligible or no increase in capacity.  A Notice of Exemption was filed with the OC Clerk-Recorder on January 6, 2020.  

 

FINANCIAL CONSIDERATIONS

 

Relocation of the MCSD force main is included within the scope of Westminster Boulevard Force Main Replacement, Project No. 3-62.  As the relocation is required to accommodate Sanitation District improvements, the Sanitation District is responsible for the associated costs. 

 

This item has been budgeted.  (FY2019-20 Update, Appendix A, Page A-7) and the budget is sufficient for this action.

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OCSD website (www.ocsd.com) with the complete agenda package:

 

                     Sewer Relocation Agreement

 

 

JGD:dm:gc