File #: 2020-910    Version: 1 Name:
Type: Consent Status: Passed
File created: 2/5/2020 In control: OPERATIONS COMMITTEE
On agenda: 3/4/2020 Final action: 3/4/2020
Title: REDHILL RELIEF SEWER RELOCATION AT STATE ROUTE 55, PROJECT NO. FE18-13
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. FE18-13 Utility Agreement No. OCSD-1005, 3. File Summary
Related files: 2020-964, 2021-1944, 2021-1430
FROM: James D. Herberg, General Manager
Originator: Kathy Millea, Director of Engineering

SUBJECT:

title
REDHILL RELIEF SEWER RELOCATION AT STATE ROUTE 55, PROJECT NO. FE18-13
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION: Recommend to the Board of Directors to:

Approve Utility Agreement No. OCSD-1005 between the Orange County Sanitation District and the Orange County Transportation Authority agreeing to specific terms, conditions, and funding obligations regarding the relocation and protection of the Redhill Relief Sewer at State Route 55 in the City of Santa Ana.

body
BACKGROUND

The Orange County Transportation Authority (OCTA) is implementing the State Route 55 Improvement Project (SR-55 Improvement Project) to widen State Route 55 between Interstate 5 and Interstate 405.

RELEVANT STANDARDS

* Maintain collaborative and cooperative relationships with regulators, stakeholders, and neighboring communities
* Protect Orange County Sanitation District assets

PROBLEM

The SR-55 Improvement Project will widen the freeway right-of-way and add a travel lane. An existing Orange County Sanitation District (Sanitation District) manhole is located where the additional lane will be constructed and the sewer under the added freeway lane is unprotected.

PROPOSED SOLUTION

Conduct a project to relocate a portion of the sewer and construct a casing at the unprotected sewer segments underneath the proposed right-of-way addition. OCTA has agreed to fund the relocation and protection of the Sanitation District sewer. To receive the funding, the Sanitation District must enter into a Utility Agreement with OCTA.

TIMING CONCERNS

The relocation and protection of the sewer must begin by June 2021 to align with OCTA's SR-55 Improvement Project's schedule.

RAMIFICATIONS OF NOT TAKING ACTION

The Sanitation District sewer may be damaged by the OCTA project.

PRIOR COMMITTEE/BOARD ACTIONS

N/A

ADDITIONAL INFORMATION

A design task order...