File #: 2023-2934    Version: 1 Name:
Type: Non-Consent Status: Passed
File created: 4/18/2023 In control: STEERING COMMITTEE
On agenda: 4/26/2023 Final action: 4/26/2023
Title: WESTMINSTER BOULEVARD FORCE MAIN REPLACEMENT, PROJECT NO. 3-62
Sponsors: Mike Dorman
Attachments: 1. Agenda Report, 2. Presentation - 3-62 Construction Contingency Increase
Related files: 2019-827, 2023-2920
FROM: Robert Thompson, General Manager
Originator: Mike Dorman, Acting Director of Engineering

SUBJECT:

title
WESTMINSTER BOULEVARD FORCE MAIN REPLACEMENT, PROJECT NO. 3-62
end

GENERAL MANAGER'S RECOMMENDATION

recommendation
RECOMMENDATION:

A. Approve a project budget increase of $900,000 for Westminster Boulevard Force Main Replacement, Project No. 3-62, for a new total project budget of $43,900,000; and

B. Approve a contingency increase of $1,109,720 (4%) to the existing Construction Agreement with Teichert Energy & Utilities Group, Inc. for Westminster Boulevard Force Main Replacement, Project No. 3-62, for a new total contingency amount of $3,884,020 (14%).
body

BACKGROUND

The Westminster Boulevard Force Main Replacement, Project No. 3-62, replaced two force mains that run from the Seal Beach Pump Station at the intersection of Seal Beach Boulevard and Westminster Boulevard in the City of Seal Beach, to the intersection of Westminster Boulevard and Rancho Road in the City of Westminster, a distance of approximately 14,000 feet.

All pipeline installation work is complete and beneficial use of the new force mains was achieved in December 2022. Contract-required asphalt and landscaping restoration efforts were recently completed.

RELEVANT STANDARDS

* Ensure the public's money is wisely spent
* Maintain collaborative and cooperative relationships with regulators, stakeholders, and neighboring communities
* Sound engineering and accounting practices, complying with local, state, and federal laws

PROBLEM

Construction of the new force mains required shifting of vehicular traffic onto existing bike lanes for several months to create space for pipeline installation. Vehicle traffic compounded by nearby I-405 construction and heavy rain in 2023 caused unanticipated asphalt damage to the existing bike lane. The project has achieved substantial completion and needs to restore the existing bike lanes to mitigate delays to project com...

Click here for full text