File #: 2022-2055    Version: 1 Name:
Type: Information Item Status: Filed
File created: 12/14/2021 In control: STEERING COMMITTEE
On agenda: 1/26/2022 Final action: 1/26/2022
Title: HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO. P1-128A
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. Presentation - Headquarters Update
Related files: 2022-2543, 2022-2250

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO. P1-128A

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION: 

Information Item.

body

 

BACKGROUND

 

Project No. P1-128A, Headquarters Complex, will construct a New Headquarters Building on the north side of Ellis Avenue to house administrative and engineering staff.  The Headquarters Complex will also include a Board Room and a pedestrian/utility bridge over Ellis Avenue to Plant No. 1.

 

Construction started in July 2021 and completion is scheduled for December 2023.

 

Staff will present an update on the construction progress.

 

RELEVANT STANDARDS

 

                     Provide a safe and collegial workplace

                     Ensure the public’s money is wisely spent

 

ATTACHMENT

The following attachment(s) may be viewed on-line at the OC San website (www.ocsan.gov) with the complete agenda package:

 

                     Presentation

 

AB:jw