Title: HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO. P1-128A - QUARTERLY UPDATE
Sponsors: Kathy Millea
Attachments: 1. Agenda Report, 2. Presentation - Headquarters Update
Related files: 2022-2055, 2020-1300, 2019-576, 2022-2543, 2022-2418

FROM:                     James D. Herberg, General Manager

                     Originator: Kathy Millea, Director of Engineering 

 

SUBJECT:

 

title

HEADQUARTERS COMPLEX AT PLANT NO. 1, PROJECT NO. P1-128A - QUARTERLY UPDATE

end

 

GENERAL MANAGER'S RECOMMENDATION

 

recommendation

RECOMMENDATION:

Information Item.

body

 

BACKGROUND

 

Project No. P1-128A, Headquarters Complex, will construct a new Headquarters Building on the north side of Ellis Avenue to house administrative and engineering staff.  The Headquarters Complex will also include a Board Room and a pedestrian/utility bridge over Ellis Avenue to Plant No. 1.

 

Construction started in July 2021 and completion is scheduled for December 2023.  Staff will present an update on the construction progress.

 

RELEVANT STANDARDS

 

                     Provide a safe and collegial workplace

                     Ensure the public’s money is wisely spent

                     Comply with current Building Codes

 